For an energy-project sponsor, the useful question in DOE's December 15, 2016 rulemaking is what separates an eligible proposal from a completed financing arrangement. The department revised its Title XVII loan-guarantee regulations, with effectiveness set for January 17, 2017. It did not turn an application into a commitment to supply a project's capital. [2016-30006][2016-23268]

The October 3 proposal provides a concrete view of the intended closing discipline. It proposed that, prior to or on the closing date, the Credit Subsidy Cost be covered through an appropriation, full payment of that cost by the borrower, or a combination. The timing includes the closing date itself. The phrase full payment concerns the credit subsidy cost, not a requirement that the borrower fund the entire project alone. [2016-30006][2016-23268]

The final rule supplies another boundary for financing plans: expected principal of Guaranteed Obligations, estimated when issued, cannot exceed 80 percent of the eligible project's defined Project Costs. Sponsors therefore cannot read eligibility as an automatic entitlement to a particular amount. This cap and the proposed subsidy-cost condition concern different elements of the arrangement and should not be collapsed into one percentage. [2016-30006][2016-23268]

The project must also fit the program's environmental and technology criteria, including new or significantly improved technology relative to commercial technology in use in the United States. That keeps execution tied to the specific project rather than a broad innovation label. Proposal and final text belong to one agency process; neither establishes that a sponsor secured financing, completed construction or delivered the environmental gains DOE sought. [2016-30006][2016-23268]

Source documents

  1. Loan Guarantees for Projects That Employ Innovative Technologieshttps://www.govinfo.gov/content/pkg/FR-2016-12-15/html/2016-30006.htm
  2. Loan Guarantees for Projects That Employ Innovative Technologieshttps://www.govinfo.gov/content/pkg/FR-2016-10-03/html/2016-23268.htm