A project plan labeled dam removal can contain several legally distinct activities. The Corps' January 6, 2017 rule creates Nationwide Permit 53 for removing low-head dams, with pre-construction notification required. It does not itself authorize nearby stream restoration or bank stabilization. Disposal of the removed structure in waters of the United States also requires separate district-engineer authorization. [2016-31355]
The operative question for execution is therefore which authorization covers each part of the work. The removal permit requires the dam material to be deposited and retained outside those waters unless separately approved otherwise. General, regional and case-specific conditions continue to apply. The new route is tied to the nationwide program's minimal individual and cumulative adverse-effects standard, not unrestricted clearance for an entire redevelopment plan. [2016-31355]
Transition rules are another planning boundary. The June 1, 2016 proposal explained that qualifying activities already authorized under 2012 nationwide permits, begun or under contract to commence by March 18, 2017, would have until March 18, 2018 to finish under those permits' terms. The final document retained that explanation. Completed authorized activities remain authorized; other unfinished work needs qualifying reauthorization or another suitable permit. [2016-31355][2016-12083]
The new and reissued permits were originally scheduled to begin March 19, 2017 and expire March 18, 2022. Those dates do not extend every earlier project automatically. Proposal and final rule form one administrative record, rather than independent assurance that any particular applicant qualifies. For institutions budgeting the work, distinguishing activity scope from transition eligibility makes the authorization question specific enough to examine. [2016-31355][2016-12083]
Source documents
- Issuance and Reissuance of Nationwide Permitshttps://www.govinfo.gov/content/pkg/FR-2017-01-06/html/2016-31355.htm
- Proposal To Reissue and Modify Nationwide Permitshttps://www.govinfo.gov/content/pkg/FR-2016-06-01/html/2016-12083.htm