The Cabinet Office’s Procurement Policy Note 04/19, issued on 23 July, updates the government’s approach to payment practices in major contracts. It assigns the implementation task to central government departments, executive agencies and non-departmental public bodies—not to every public buyer or every UK contract. The note replaces PPN 04/18 and frames payment-system assessment as part of procurement rather than a blanket supplier ban. [shared-bb88f9b7e8edd3bfa6fad1534e388ba09a727491d9218b0011221e4e34f18300]

The policy applies to relevant goods, services and works procurements subject to the Public Contracts Regulations 2015 when anticipated value exceeds £5 million per annum, excluding VAT, unless exceptional circumstances make application irrelevant or disproportionate. That figure is an annualised scope boundary, not a payment-days or payment-percentage test. For framework agreements and dynamic purchasing systems, the test concerns the anticipated value of each individual contract. [shared-bb88f9b7e8edd3bfa6fad1534e388ba09a727491d9218b0011221e4e34f18300]

The provisions apply to relevant procurements advertised on or after 1 September 2019. In-scope organisations are to put the questions into section 6.2 of the standard selection questionnaire; works procurement continues to use PAS91 with a project-specific question. The accompanying guidance explains assessment of payment systems and when exclusion may be appropriate. Procurement teams must apply the stated scope and exceptions consistently, without deterring competition beyond the policy’s remit. [shared-bb88f9b7e8edd3bfa6fad1534e388ba09a727491d9218b0011221e4e34f18300]

Source documents

  1. Procurement Policy Note 04/19: Taking account of a supplier’s approach to payment in the procurement of major contractshttps://assets.publishing.service.gov.uk/media/5d36bc25e5274a400ce4c1b4/PPN_0419_FOR_PUBLICATION.pdf