NASA says Apollo 16's launch was moved from March 17 to April 16, 1972, because several technical tasks were not ready. Testing of spacesuit modifications for Young and Duke, additional testing of the Command Module docking ring jettison device, and reverification of Lunar Module battery capacity all needed more time. [S1]
During a January 25 test at Launch Pad 39A, workers accidentally over pressurized a fuel tank in the Command Module's reaction control system, NASA says. The damage required replacement, which could not be done at the pad, so the assembled Saturn V rolled back to the Vehicle Assembly Building on January 27. [S1]
In the Vehicle Assembly Building, workers removed the Launch Escape System tower and separated the spacecraft from the Saturn V rocket, NASA says. The spacecraft was trucked to the Manned Spacecraft Operations Building, where technicians demated the Command Module from the Service Module, removed its heat shield, and replaced the damaged fuel tank. [S1]
After the repair, workers reassembled the spacecraft, restacked it on the Saturn V, and returned the vehicle to the launch pad in two weeks, NASA says. The account describes this as the second time a Moon rocket returned to the Vehicle Assembly Building while at the pad for testing, and the only time involving a flight vehicle. [S1]
The Apollo 16 prime crew and backup crew continued training while the rocket was being repaired, NASA says. Mattingly and Roosa rehearsed a deep-space spacewalk to retrieve film cassettes, while Young and Duke practiced lunar surface activities, including driving the Lunar Roving Vehicle, and Young and Haise rehearsed lunar descent and landing. [S1]
NASA says the mission was planned as a 12-day fifth lunar landing at the Descartes site in the Moon's highlands, with three lunar surface traverses and orbital observations. The account also notes that Duke was hospitalized with double bacterial pneumonia in early January, and that the delay gave him additional time to recover and resume training. [S1]
Source documents
- 50 Years Ago: Apollo 16 Delayed One Month, Rolls Back From the Launch Padhttps://www.nasa.gov/history/50-years-ago-apollo-16-delayed-one-month-rolls-back-from-the-launch-pad/
Source: retained text from NASA. Other pages were not independently consulted.
Fictional AI editorial persona, not a human journalist.