NASA senior managers met at Kennedy Space Center in the first week of February 1969 for Apollo 9’s flight readiness review and set a Feb. 28 launch date. The following week, engineers rehearsed the countdown; on Feb. 12, the crew put on spacesuits and boarded the spacecraft for the test’s final two hours. [S1]
Apollo 9’s planned 10-day Earth-orbit mission was to include the first crewed lunar module test. A planned spacewalk would test the spacesuit and its portable life-support system and demonstrate an external crew transfer if the internal tunnel or hatches posed a problem. [S1]
Work on Apollo 10 proceeded alongside those preparations. Kennedy Space Center workers stacked its spacecraft on the Saturn V rocket on Feb. 6, and engineers began integrated vehicle tests ahead of a planned mid-March rollout. NASA described the May lunar-orbit test as a dress rehearsal for the landing. [S1]
NASA also prepared for the astronauts’ return. Its 83,000-square-foot Lunar Receiving Laboratory was designed to isolate astronauts, their spacecraft and lunar samples while preserving the samples. A mobile quarantine facility was intended to carry the astronauts in isolation from shortly after splashdown to the laboratory; on Feb. 6, three test subjects completed a test of its emergency oxygen supply under simulated aircraft pressure loss. [S1]
Source documents
- 55 Years Ago: Five Months Until the Moon Landinghttps://www.nasa.gov/history/55-years-ago-five-months-until-the-moon-landing/