The rehearsal is designed to test the launch team’s ability to load more than 700,000 gallons of cryogenic propellant, run a countdown, and safely remove the fuel without astronauts aboard. It will also test stopping, resuming, and restarting countdown operations at several points in the final 10 minutes. [S1]
After the rehearsal, NASA’s mission management team is to assess the flight hardware, launch infrastructure, and launch, flight, and recovery personnel before committing to a date. The report describes early February as a possible opening for the launch window, not a selected date. [S1]