The operational handoff had two stages. The interagency transfer became effective Feb. 23, 2026; after that, NASA completed closeout work by removing the parcel’s buildings, roadway and utility service. The July 7 ceremony marked the transfer publicly, while the report describes the earlier effective date and completed site work. [S1]
Area 400 had supported propellant research beginning in the 1960s. NASA says much of that work had shifted to facilities in other states or commercial providers, and the agency and the U.S. Fish and Wildlife Service began discussing a potential transfer in 2021. The report therefore documents a completed property disposition following a multi-year interagency process, rather than a newly announced proposal. [S1]
Source documents
- NASA Transfers ‘Hundred Acre Wood’ to Patuxent Research Refugehttps://www.nasa.gov/centers-and-facilities/goddard/nasa-transfers-hundred-acre-wood-to-patuxent-research-refuge/